New Building
Phase 4 Progress Report
Construction of the New Building is now underway and this space will be dedicated to a photographic record of progress in the months ahead. Members should notice the building going up quite quickly behind the Family Clubhouse, on the space formerly occupied by Tennis Court 1. As such, the building has a rather small “footprint”, although the upper floors are cantilevered to accommodate the two covered tennis courts. At the time of writing, we anticipate a phased opening of the building in May-June 2006.

Interpreting the photos
You will notice that most photos refer to different levels, beginning with level 4. Due to the sloped nature of our site, level 4 represents the first level of the New Building, which is dedicated to staff use. Level 5 includes the bowling alley and café. Level 6 and Upper Level 6 accommodate junior activity areas, the library and management offices, while Level 7 is dedicated to the spa. The new spa promises to be the first of its kind for a private club in Asia, with facilities and treatments similar to those offered in the finest hotels and resorts. The top of the building is dedicated to two covered tennis courts. A sectional (side view) plan of the building is included for your reference.

Phase 5
The New Building represented Phase 4 of the multi-year five phase building programme. Previous phases have addressed the Ladies’ Changing Room, gym, Boys’ and Girls’ Changing Rooms, Family Clubhouse, etc. Once the New Building opens, the offices, Library and Reading Room will move to the New Building, facilitating the renovation of the Main Clubhouse.

Renderings
Five-Star Spa for Gentlemen & Ladies
• An Interview with Our Spa Consultant Sean O'Connor


Bowling Alley & Snack Bar
• An Interview with Our Recreation Manager Wesley Caballa

A Junior Activity Floor with Studios for Classes

• An Interview with Our Activities Co-ordinator Kelly Man

Library with Computer Terminals

Our New Covered Tennis Courts & the Restoration of Court 2

Section Plan

Work in Progress
The following photos show the work in progress, in reverse chronological order. This means that the most recent pictures are shown first. This way, it is easy for you to track the development on an ongoing basis by looking at the most recent photographs.

Photos taken on 20 June 2006  
Polyurethane paint to steel truss on Upper Roof in progress. Fire resisting paint to steel posts on Upper Roof in progress.
Photos taken on 9 May 2006  
External mosaic tiling to staircase ST-2 in progress. Steel framework for chain link fencing to Tennis Court No. 2
on Level 4 in progress.
Photos taken on 21 March 2006  
Mansory wall at Lev. 4 completed.
Erection of steel truss on upper roof completed.
Photos taken on 7 March 2006  
Erection of main truss on upper roof in progress. Painting to beam and ceiling to Tennis Court No. 1 on
lower roof completed.
Photos taken on 20 February 2006  
Erection of steel columns for roof truss on upper roof in progress. Concrete to extension of existing gravity wall completed.
Photos taken on 7 February 2006  
Linking bridge between new Clubhouse and Lift No. L1 completed. Re-bar fixing to remaining part of gravity wall extension completed and formwork erection in progress.
Photos taken on 16 January 2006  
Re-bar and formwork extension of existing gravity wall
in progress.
Re-bar and formwork to think bridge between new annex
block and lift L1 completed.
Photos taken on 3 January 2006  
Erection of steel frame for extension of existing gravity wall
in progress.
Construction of concrete link bridge between Lift No. 1 and
new Clubhouse in progress.
Photos taken on 19 December 2005  
Removal of top part of existing gravity wall for A&A works completed. Steel channel supporting frame for blockwall partition at
Lev. 7 completed.
Photos taken on 14 November 2005  
Formwork and re-bar fixing from upper roof to top roof of staircase ST-2 in progress. Concrete to beam and slab between Grid 'C' to 'G' at upper roof completed.
Photos taken on 20 September 2005  
Metal scaffolding falsework for cantilever structure
between Grid 'A' to 'D' at lower roof in progress.
Re-bar to lift shaft wall for Lift L1 in progress.
Photos taken on 6 September 2005  
Falsework for cantilevered projection at lower roof between
Grid 'D' and 'G' in progress.
Concreting to beam and slab between Grid 'A' to 'D' at Lev.
7 in progress.
Photos taken on 9 August 2005  
Concrete to r.c. slab on 'Bondek' steel decking between
Grid 'D' and 'F' at Lev. upper 6 in progress.
'Bondek' steel decking between Grid 'C' and 'D' at Lev.
Upper 6 and re-bar fixing to water tanks on Lev. 6 in progress.
Photos taken on 26 July 2005  
Construction of concrete structure from Grid 'A' to 'C' from
Lev. 6 to Lev. Upper 6 in progress. Erection of steel structure from Lev. 6 to Lev. Upper 6 in progress.
Aerial view of Lev. 6 with re-bar and concealed conduit to
beam and slab from Grid D to G in progress
Photos taken on 28 June 2005  
Formwork to wall and column from Lev. 5 to Lev. 6 in
progress
Formwork to beam and slab to Lev. 6 in progress
Photos taken on 30 May 2005  
New Building site facing toward Clovelly Court, showing excavation for ground beans. Court 2, to be restored later, to
the left
Concrete to lift pit for Lift 3 in progress