| Photos taken on 9
May 2006 |
|
 |
 |
| External
mosaic tiling to staircase ST-2 in progress. |
Steel framework
for chain link fencing to Tennis Court No. 2
on Level 4 in progress. |
| Photos taken on 21
March 2006 |
|
 |
 |
Mansory
wall at Lev. 4 completed.
|
Erection
of steel truss on upper roof completed. |
| Photos taken on 7
March 2006 |
|
 |
 |
| Erection
of main truss on upper roof in progress. |
Painting
to beam and ceiling to Tennis Court No. 1 on
lower roof completed. |
| Photos taken on 20
February 2006 |
|
 |
 |
| Erection
of steel columns for roof truss on upper roof
in progress. |
Concrete
to extension of existing gravity wall completed. |
| Photos taken on 7
February 2006 |
|
 |
 |
| Linking
bridge between new Clubhouse and Lift No. L1 completed. |
Re-bar
fixing to remaining part of gravity wall extension
completed and formwork erection in progress. |
| Photos taken on 16
January 2006 |
|
 |
 |
Re-bar
and formwork extension of existing gravity wall
in progress. |
Re-bar
and formwork to think bridge between new annex
block and lift L1 completed. |
| Photos taken on 3
January 2006 |
|
 |
 |
Erection of steel frame
for extension of existing gravity wall
in progress. |
Construction of concrete
link bridge between Lift No. 1 and
new Clubhouse in progress. |
| Photos taken on 19
December 2005 |
|
 |
 |
| Removal
of top part of existing gravity wall for A&A works
completed. |
Steel channel
supporting frame for blockwall partition at
Lev. 7 completed. |
| Photos taken on 14
November 2005 |
|
 |
 |
| Formwork
and re-bar fixing from upper roof to top roof
of staircase ST-2 in progress. |
Concrete
to beam and slab between Grid 'C' to 'G' at upper
roof completed. |
| Photos taken on 20
September 2005 |
|
 |
 |
Metal scaffolding
falsework for cantilever structure
between Grid 'A' to 'D' at lower roof in progress. |
Re-bar
to lift shaft wall for Lift L1 in progress. |
| Photos taken on 6
September 2005 |
|
 |
 |
Falsework
for cantilevered projection at lower roof between
Grid 'D' and 'G' in progress. |
Concreting
to beam and slab between Grid 'A' to 'D' at Lev.
7 in progress. |
| Photos taken on 9
August 2005 |
|
 |
 |
Concrete
to r.c. slab on 'Bondek' steel decking between
Grid 'D' and 'F' at Lev. upper 6 in progress. |
'Bondek'
steel decking between Grid 'C' and 'D' at Lev.
Upper 6 and re-bar fixing to water tanks on Lev.
6 in progress. |
| Photos taken on 26
July 2005 |
|
 |
 |
Construction
of concrete structure from Grid 'A' to 'C' from
Lev. 6 to Lev. Upper 6 in progress. Erection of
steel structure from Lev. 6 to Lev. Upper 6 in
progress. |
Aerial
view of Lev. 6 with re-bar and concealed conduit
to
beam and slab from Grid D to G in progress |
| Photos taken on 28
June 2005 |
|
 |
 |
Formwork
to wall and column from Lev. 5 to Lev. 6 in
progress |
Formwork
to beam and slab to Lev. 6 in progress |
| Photos
taken on 30 May 2005 |
|
 |
 |
New Building site facing
toward Clovelly Court, showing excavation for
ground beans. Court 2, to be restored later, to
the left |
Concrete
to lift pit for Lift 3 in progress |